After boring to specified depth (bearing layers), injecting in boring slurry,
root-hardening cement slurry is pumped in to a boring tip part. Then pulling
up earth auger while fixed slurry pumping into bored hole, it builds to
a hole and a pile is installed into root hardening slurry by pressing or
light blowing.
By root hardening and round of pile fixed slurry, a pile and the layers
are made to unify and bearing capacity is ensured. Although it can piling
works in low vibration and low noise.
For application pile diameter, about 300-600mm and the maximum pile
length are about 35m.
|